Scottish Water has commenced the search for contractors to construct a major processing facility in Scotland, anticipated to significantly impact the region’s wastewater treatment capabilities.
- The envisaged processing facility is set to handle 85,000 tonnes of dry solids annually, enhancing efficiency in waste management.
- The project, estimated between £185m and £285m, will adopt a collaborative design-and-build approach involving various stakeholders from the project’s inception.
- Interested parties, including joint ventures and consortiums, are required to demonstrate prior experience in similar large-scale infrastructure projects.
- A bidders’ information day is scheduled, indicating proactive engagement and transparency in the contracting process.
Scottish Water has initiated the procurement process for a substantial new processing facility in central Scotland, a move poised to bolster the region’s wastewater management capabilities. The facility is expected to process approximately 85,000 tonnes of dry solids each year, representing a significant upgrade in existing infrastructure.
The project’s financial scope is projected to range from £185 million to £285 million. This initiative will follow a design-and-build model, incorporating early contractor involvement in a two-stage tender process. This approach facilitates extensive collaboration among stakeholders, encouraging comprehensive design and operational planning from the outset.
In an official notice dated 17 July, Scottish Water has extended an invitation to joint ventures, consortiums, and other collaborative entities to partake in the tender. Prospective contractors must possess a proven track record in delivering and commissioning comparable infrastructure projects, ensuring the selection of competent and experienced firms.
The first stage of the tender is poised to commence with a contract notice expected by 12 August, setting in motion subsequent construction activities anticipated to begin in April 2027. This timeline underscores Scottish Water’s forward-planning to integrate the new facility seamlessly into existing operations.
Once operational, the site is expected to produce a class-A bioresource product, which holds the potential for recycling and application in agricultural land. The emphasis on maximising energy recovery and minimising the carbon footprint aligns with broader sustainability objectives.
Scottish Water is scheduled to host a bidders’ information session on 8 August at Glasgow’s Principal Grand Central Hotel, facilitating direct engagement with potential contractors. Prospective companies are required to register their attendance by contacting Scottish Water by 2 August, demonstrating procedural thoroughness and organisational transparency.
This significant investment by Scottish Water marks a transformative step towards enhanced waste management and sustainable resource use in Scotland.